| Role | Name | Responsibility |
|---|---|---|
| Site Supervisor | Overall site control, WHS compliance, toolbox talks, incident reporting | |
| Leading Hand | Supervise work tasks, enforce controls, coordinate plant and personnel | |
| Workers | Perform work as directed, comply with SWMS, report hazards immediately | |
| Spotter / Dogman | Exclusion zone enforcement, plant spotting, communication with operator |
| # | Work Step | Hazards Identified | Initial Risk | Control Measures | Residual Risk | Responsible |
|---|---|---|---|---|---|---|
| 1 | Conduct site induction and review Dial Before You Dig plans. | Unawareness of underground services leading to potential strikes. | H | Ensure all workers are briefed on underground service locations and plans are available on site. | M | Site Supervisor |
| 2 | Mobilise 5-tonne excavator to the site. | Collision with existing structures or personnel during mobilisation. | M | Use a spotter to guide the excavator into position, ensuring clear communication. | L | Leading Hand |
| 3 | Begin excavation of footings to a depth of 1.8 metres. | Cave-ins or collapse of excavation walls. | H | Install shoring progressively as excavation depth increases. | M | All Workers |
| 4 | Monitor excavation work adjacent to existing structure. | Damage to existing structure due to vibration or undermining. | H | Maintain a safe distance from the structure and monitor for any signs of movement or damage. | M | Site Supervisor |
| 5 | Use spotter to assist during excavation near underground services. | Striking underground services causing service disruption or hazards. | H | Spotter to maintain visual contact with excavation and alert operator to any potential service locations. | M | Leading Hand |
| 6 | Demobilise equipment and clear site. | Injury from equipment movement or site debris. | M | Ensure all equipment is safely shut down and debris is cleared from the site. | L | All Workers |
I have read and understood this SWMS. I agree to perform all work in accordance with the controls and procedures described.
| Name (Print) | Role | Signature | Date |
|---|---|---|---|
| Role | Name | Signature | Date |
|---|---|---|---|
| Prepared By | Atlas (Draft) | 07 May 2026 | |
| Reviewed By (Site Supervisor) | |||
| Approved By (Head of Construction) | Elliot Marsh |